2018 Street Improvements

Project Description:

Road improvements for this project include:
  • S 2nd St (from Kincaid St, entire intersection, to Blackburn Rd) - Park St to Old 99 PAVED 9/25/18
  • Old Hwy 99 (small portion south of Blackburn at the R/R tracks)
  • Section St (Laventure Rd - 18th St) - PAVED 8/6/18
  • Section St (18th St west - Denny St) - PAVED 8/9/18
  • S Laventure Rd (Section to Fowler St) - PAVED 8/3/2018
  • Warren St (N 6th St to Dead End east of N 11th St) - PAVED 8/2/2018
Funding: 
City Funded - Transportation Benefit District

Project Status:
SRV Construction started work the 2018 Street Improvements project the week of July 16th. The project is expected to be complete in mid October 2018.

The contractor has completed paving on Warren Street, Laventure and on Section St.  On Monday, September 26th, they will begin excavating and rebuilding portions of 2nd Street. This work will last approximately 2-3 weeks and will require temporary road closures to accommodate the work.  Paving is expected the week of October 22nd. Following paving, crews will still need to stripe and raise utilities so construction will continue, but roads should remain open with only limited lane closures. 