Kulshan Trail Safety Lighting (Riverside Drive to 18th Street)


Bid Award: December 9, 2020 - $134,488

Contractor: Oceanside Construction, Inc., Bellingham, WA 

Consulting Firm: Transpo Group USA, Inc., Kirkland, WA

Project Engineer: William Bullock PE, MPA, City Engineer 

Contact Information: (360) 336-6204

Funding: Funding for this project is through the Federal Highway Administration (FHWA).


Sign up here for Construction and Road Closure Notifications

Additional Documentation

The City of Mount Vernon, Washington is solicited interest from consulting firms with expertise in civil, surveying, electrical engineering, and other related professional services. The City is preparing to begin design efforts on the lighting improvements to the Kulshan trail between Riverside Drive and 18th Street in include street style lighting, underground power, and security camera amenities. 


Current Status:

Construction began on January 4, 2021. Conduit installation is expected to be complete by the first week of February, then Puget Sound Energy will begin installing the light fixtures soon after.