College Way & 30th Street Signal


Bid Award: June 26, 2019 - $805,546.20

Contractor: Larry Brown Construction, Bellingham, WA

Construction Management: Reichhardt & Ebe Engineering, Lynden, WA

Project Engineer: William Bullock PE, MPA, City Engineer 

Contact Information: (360) 336-6204

Funding: Funding for this project is through the Federal Highway Administration (FHWA).


Sign up here for Construction and Road Closure Notifications

Additional Information 

Vicinity Map
This project included construction of a signal at the intersection of College Way and 30th Street, including ADA improvements, utility relocation, traffic analysis, signal coordination, and travel lane realignment.

Current Status:
This project was completed on October 22, 2020, in the amount of $813,054.41.