Cedardale/Anderson Road Roundabout (2019 Street and Curb Ramp Improvements)

Bid Award: September 11, 2019 - $330,368.00
Contractor: Pellco Construction, Inc., Mukilteo, WA

Construction Management: City of Mount Vernon
Project Engineer: Darin Christen, PE, Senior Project Engineer
Contact Information: (360) 336-6204
Funding: Transportation Benefit District


Additional Information

Sign up here for Construction and Road Closure Notifications

Project Description:
This project included improvements to the Cedardale and Anderson Roads roundabout.

Current Status:

The project was completed on March 12, 2020, for a total cost of $422,010.49