2020 Sanitary and Storm Sewer Lining

Project Description:
This project includes lining approximately 8,273 feet of sanitary sewer pipe and approximately 948 feet of storm sewer pipe with a cured in place pipe (CIPP) liner system. Work also includes grouting and restoring laterals, trimming intruding laterals, and lining pipe with manholes near a railroad and in I-5.

Funding:
Utility Funded

Project Information:
This project was released for bid on February 11, 2020. Bids are due by 10:00 am March, 4, 2020, and this page will be updated at that time. 

Project Update (2/12/2020):
No Updates

Additional Information

Sign up here for Construction and Road Closure Notifications