Schedule of work 1/28/14 to 2/4/14:
Strider Construction will continue setting concrete forms, placing rebar, and concrete for the floodwall. Demolition of the revetment parking structure south of Myrtle Street will continue.
Utility companies continue to relocate infrastructure to an underground system.
Demolition of the Moose Lodge building and installation of a new storm drain system will begin next week.
This project remains on schedule to be complete by September 2014.