News Flash Home
The original item was published from 11/20/2013 2:04:00 PM to 12/10/2013 12:05:00 AM.

News Flash

News & Announcements

Posted on: September 18, 2013

[ARCHIVED] Downtown Flood Protection & Revitalization Project, Phase II Project Update

new sidewalk

Schedule of work 11/19/13 to 12/2/13:

Strider Construction will continue setting concrete forms, placing rebar, and concrete for the floodwall.

The new parking area was paved last week and is planned to be open by Thanksgiving. Concrete sidewalk will be installed adjacent to the parking area this week. The Landscape contractor will start placing topsoil in preparation for planting.

Strider Construction will be performing minor work activities the week of Thanksgiving. December 2nd work will begin to install an underground utility system on Main Street between Gates and Pine Street. Partial road closures of Main Street will be required as this work progresses.

This project remains on schedule to be complete by September 2014.

For questions contact:
City of Mount Vernon Public Works Department
(360) 336-6204
mvengineering@mountvernonwa.gov

Additional Info...
Facebook Twitter Email

Other News in News & Announcements