Schedule of work 12/10/13 to 12/20/13:
Strider Construction will continue setting concrete forms, placing rebar, and concrete for the floodwall with a scheduled concrete pour this week.
The new parking area south of Division Street and west of Main Street was opened to the public the week of Thanksgiving.
Strider Construction will complete the underground utility work on Main Street between Gates and Pine Street this week. A temporary asphalt patch will be placed over the trench until further construction activities begin in January.
This project remains on schedule to be complete by September 2014.