[ARCHIVED] Downtown Flood Protection & Revitalization Project, Phase II Project Update

floodwall progress

Schedule of work 1/14/14 to 1/21/14:

Strider Construction will continue setting concrete forms, placing rebar, and concrete for the floodwall. In the upcoming weeks Strider will be adding resources to continue the revetment demolition, underground utility work on Main Street, and begin the Moose Lodge demolition.

Potelco Construction continues work to relocate the power utility underground.

Skagit PUD will start work to install a new waterline on Main Street between Gates and Myrtle.

This project remains on schedule to be complete by September 2014.

For questions contact:

City of Mount Vernon Public Works Department
(360) 336-6204
mvengineering@mountvernonwa.gov