Schedule of work 1/22/14 to 1/28/14:
Strider Construction will continue setting concrete forms, placing rebar, and concrete for the floodwall. Demolition of the revetment parking structure began Monday.
Utility companies will continue to relocate infrastructure to an underground system.
Upcoming work includes demolition of the Moose Lodge Building, installation of a storm drain system and waterline on Main Street.
This project remains on schedule to be complete by September 2014.