[ARCHIVED] Downtown Flood Protection & Revitalization Project, Phase II Project Update

Waterfront Trail Grading

Schedule of work 3/5/14 to 3/12/14:

Strider Construction will continue with installation of the concrete walkway adjacent to the river.

The installation of the steel sheet piling for the south half of the floodwall is complete and work will begin on the concrete floodwall foundation.

This project remains on schedule to be complete by September 2014.

For questions contact:

City of Mount Vernon Public Works Department
(360) 336-6204
mvengineering@mountvernonwa.gov