Schedule of work 3/11/14 to 3/18/14:
Strider Construction will continue with installation of the concrete walkway adjacent to the river. Main Street road construction will begin this week starting with the removal of asphalt. Work will also continue on the concrete floodwall foundation.
Monday, March 17th, Main Street between Myrtle and Gates Street will be closed to vehicle traffic and construction of the pedestrian plaza park will begin.
This project remains on schedule to be complete by September 2014.
For questions contact: