Schedule of work 3/18/14 to 3/25/14:
Strider Construction continues work on the concrete walkway, and floodwall adjacent to the river.
Intermittent road closures of Main Street will be required as work continues with removal of asphalt and installation of curb.
Main Street between Myrtle and Gates Street is closed to vehicle traffic for construction of the pedestrian plaza park.
This project remains on schedule to be complete by September 2014.