Schedule of work 3/25/14 to 4/1/14:
Strider Construction continues work on the concrete walkway, and floodwall adjacent to the river.
Intermittent road closures of Main Street will be required this week as work continues with placing gravel and installation of curb in preparation for paving.
Main Street between Myrtle and Gates Street is closed to vehicle traffic for construction of the pedestrian plaza park.
This project remains on schedule to be complete by September 2014.
For questions contact:
City of Mount Vernon Public Works Department
(360) 336-6204