Schedule of work 4/15/14 to 4/22/14:
Strider Construction continues work on the concrete walkway, and floodwall adjacent to the river. Contractor will begin applying decorative brick to the floodwall.
Main Street between Myrtle and Gates Street is closed to vehicle traffic for construction of the pedestrian plaza park. Installation of the underground storm tank system will begin this week.
This project remains on schedule to be complete by September 2014.