News Flash Home
The original item was published from 4/15/2014 1:54:00 PM to 4/22/2014 2:08:15 PM.

News Flash

News & Announcements

Posted on: December 10, 2013

[ARCHIVED] Downtown Flood Protection & Revitalization Project, Phase II Project Update

removing floodwall forms

Schedule of work 4/15/14 to 4/22/14:

Strider Construction continues work on the concrete walkway, and floodwall adjacent to the river. Contractor will begin applying decorative brick to the floodwall.

Main Street between Myrtle and Gates Street is closed to vehicle traffic for construction of the pedestrian plaza park. Installation of the underground storm tank system will begin this week.

This project remains on schedule to be complete by September 2014.

For questions contact:

City of Mount Vernon Public Works Department
(360) 336-6204
mvengineering@mountvernonwa.gov

Additional Info...
Facebook Twitter Email

Other News in News & Announcements