[ARCHIVED] Downtown Flood Protection & Revitalization Project, Phase II Project Update

plaza tree well

Schedule of work 6/10/14 to 6/17/14:

Strider Construction continues work on the concrete walkway, and floodwall adjacent to the river. Decorative brick installation will continue north of the plaza park. Overhead walkway lighting will continue this week.

Main Street between Myrtle and Gates Street is closed to vehicle traffic for construction of the pedestrian plaza park. Plaza work continues with irrigation system and decorative seating wall construction.

This project remains on schedule to be complete by September 2014.