concrete walkway

Schedule of work 7/1/14 to 7/8/14:

Strider Construction continues work on the concrete walkway, and floodwall adjacent to the river. Decorative brick will be inlaid within the walkway. Overhead walkway lighting will continue this week.

Main Street between Myrtle and Gates Street is closed to vehicle traffic for construction of the pedestrian plaza park. Plaza work continues with irrigation system and decorative seating wall construction. Sidewalk demolition on the east boundary of the plaza is scheduled to begin this week.

This project remains on schedule to be complete by September 2014.

For questions contact:

City of Mount Vernon Public Works Department
(360) 336-6204
mvengineering@mountvernonwa.gov

Additional Info...
Facebook Twitter Email

Other News in News & Announcements