Schedule of work 7/15/14 to 7/22/14:
Strider Construction continues work on the concrete walkway, and floodwall adjacent to the river. Decorative brick will be inlaid within the walkway.
Main Street between Myrtle and Gates Street is closed to vehicle traffic for construction of the pedestrian plaza park. Plaza work continues with irrigation system and decorative seating wall construction. Sidewalk construction adjacent to Main Street will begin this week.
This project remains on schedule to be complete by September 2014.
For questions contact:
City of Mount Vernon Public Works Department
(360) 336-6204
mvengineering@mountvernonwa.gov