Schedule of work 9/2/14 to 9/9/14:
Strider Construction continues work on the lower plaza concrete, decorative brick on the floodwall, and walkway lighting.
Main Street between Myrtle and Gates Street is closed to vehicle traffic for construction of the pedestrian plaza park. Plaza work continues with grading and preparation to place pervious brick pavers and flagstone. The sidewalk between Gates and Myrtle is open to pedestrian traffic.
This project remains on schedule to be complete by September 2014.
For questions contact:
City of Mount Vernon Public Works Department
(360) 336-6204
mvengineering@mountvernonwa.gov