News Flash Home
The original item was published from 9/8/2014 4:54:00 PM to 9/15/2014 4:21:38 PM.

News Flash

News & Announcements

Posted on: December 10, 2013

[ARCHIVED] Downtown Flood Protection & Revitalization Project, Phase II Project Update

lower plaza

Schedule of work 9/8/14 to 9/15/14:

Strider Construction continues work on the lower plaza concrete, decorative brick on the floodwall, and walkway lighting. Final paving of the project is scheduled for Friday including the south parking area.

Main Street between Myrtle and Gates Street is closed to vehicle traffic for construction of the pedestrian plaza park. Plaza work continues with placing pervious brick pavers and flagstone. The sidewalk between Gates and Myrtle is open to pedestrian traffic.

This project remains on schedule to be complete by September 2014.

For questions contact:

City of Mount Vernon Public Works Department
(360) 336-6204
mvengineering@mountvernonwa.gov

Additional Info...
Facebook Twitter Email

Other News in News & Announcements