Schedule of work 9/15/14 to 9/22/14:
Strider Construction continues work on the decorative brick on the floodwall, and brick inlay along the river walk. Final paving of the project is complete and paint striping is scheduled for Tuesday, September 16th. Parking areas will be blocked off to allow for the work.
Main Street between Myrtle and Gates Street is closed to vehicle traffic for construction of the pedestrian plaza park. Plaza work continues with placing pervious brick pavers and flagstone. The sidewalk between Gates and Myrtle is open to pedestrian traffic.
The project schedule has been extended to be complete by mid October 2014.