[ARCHIVED] Downtown Flood Protection & Revitalization Project, Phase II Project Update

Flagstone

Schedule of work 9/22/14 to 9/29/14:

Strider Construction continues work on the decorative brick on the floodwall, and handrail along the river walk. New parking areas along Main Street opened this afternoon.

A portion of the new pedestrian plaza park is open to the public. Plaza work will continue with construction of the flagstone patio areas and placing the last remaining concrete as weather permits this week.

The project will be open to the public by mid October.

For questions contact:

City of Mount Vernon Public Works Department
(360) 336-6204